Switchboard Factory Acceptance Test: A Buyer’s Checklist

A switchboard factory acceptance test (FAT) gives buyers a chance to review the finished assembly before it ships. For a low voltage distribution project, the most useful starting point is the approved drawing set and a test plan that states what the supplier will demonstrate. Agree both early, especially if the end client or a third party will witness the inspection.

Agree the scope of the switchboard factory acceptance test

First, identify the boards covered by the test. Use the same panel references as the single-line diagram and the purchase order. Then agree the checks, acceptance criteria, witness arrangements and records for each board. A main distribution board and a sub-main board may need different demonstrations because they serve different circuits.

Ask the supplier to distinguish the routine verification records for the finished assembly from the checks the buyer will witness. If the specification calls for separate design verification evidence, list that as a separate document request in the purchase order.

Bring the approved drawings and component list

Compare the panel labels, enclosure layout, cable entry and feeder arrangement with the approved drawings. Also check the installed component makes and model numbers against the agreed bill of materials. If the supplier proposed a substitution, confirm that the buyer approved it and that the final documents reflect it.

For example, if a feeder requires a specific breaker accessory, look for that accessory in the component list and in the relevant functional demonstration. This makes it easier to connect what was quoted to what the supplier built.

Witness the functions your project needs

Use the agreed test plan to identify which functions the factory team should demonstrate. These may include local controls, status indication, metering, alarms and interlocks, where specified. For signals that connect to equipment elsewhere on site, agree what the team can demonstrate at the factory and what will be verified during site commissioning.

For each witnessed item, record the panel reference, the expected result and the observed result. If someone raises a discrepancy, record the action, owner and evidence needed to close it.

Agree what to receive before shipment

Request the signed test record, the latest drawings, the final component schedule and any outstanding inspection records specified in the order. In addition, agree which open items require reinspection or written evidence before release. A short closeout list gives the buyer, supplier and site team the same record before delivery.

Planning a low voltage switchboard order?

Send your panel schedule, single-line diagram and witness requirements to Kathy at kathy@nbhh-group.com. Henghui can review the proposed supply and inspection scope with you. View Henghui’s Low Voltage Power Distribution Cabinet.

If you are still preparing the enquiry, see the Low Voltage Switchboard RFQ Checklist for Buyers.

Verwandte Produkte

Es wurden keine Ergebnisse gefunden.